Learn the best first step when two stakeholders demand incompatible features under a fixed deadline.
Two key stakeholders submit conflicting requirements: Sales wants a rushed feature for a demo next week, while Engineering insists it needs two more weeks for stability. As the developer/PM lead, what is the most effective first step to resolve this conflict?