Understand who owns Product Backlog decisions and how refinement really works in Scrum.
A Development team lead insists that Product Backlog refinement is a mandatory, formally scheduled Scrum event that the Scrum Master must run, and that stakeholders can directly re-order items during the Sprint to reflect changing market needs. Which statement best corrects these claims per Scrum?